Tarmac 11/33 kV Substation Upgrade

Location: UK

Client Challenges

The client required upgrade works for Tarmac substation​ with minimal outages to enable continuity of supply and an efficient delivery program.​ Replacement of Paper Insulated Lead Covered (PILC) cables is also required.

H&MV's Solution

  • H&MV project managed the engineering, design, procurement, installation and commissioning of the refurbishment of the 33/11 kV substations at Tarmac.
  • The project involved the installation and commissioning of 14 ABB Unigear 500 R Cubicles, two protection panels and 11 kV circuits. H&MV was responsible for issuing the integrated test plans (ITPs), CDM appointments, temporary work registers, construction management plans, quality plans, and safety management plans. H&MV Engineering also took care of the safety and risk management throughout the project lifecycle and produced a complete set of electrical as-built drawings and handover files.
  • The project was delivered successfully, and H&MV Engineering has been awarded subsequent upgrades with Tarmac in the UK.
Share this project

Similar Projects