Kilnap 110 kV GIS Substation

Location: Ireland

Client Challenges

As part of the CON 904 Turnkey Framework, ESB required a competent  contractor for the delivery of 110 kV GIS substation at Kilnap. This project had tight timeframes for delivery which required effective and efficient project and stakeholder management.

H&MV's Solution

  • H&MV Engineering were responsible for the substation, 110 kV Gas Insulated switchgear, enabling works, civil works, electrical plant, secondary and ancillary systems, testing and commissioning, High Voltage cables and ducting
  • A full 3D model of the station is being prepared as part of the design the Engineering, Procurement and Construction delivery of the Kilnap rocess.
  • H&MV Engineering were responsible for safety & risk management throughout the project lifecycle and produced a complete set of civil and electrical as-built drawings and handover file. Responsible for issuing the Integrated Test Plans (ITPs), Construction Management Plans, Quality Plans, Safety Management Plan and Temporary Works Register.
Share this project

Similar Projects