Client Challenges

Eli Lily required the construction of a pharmaceutical production facility, with controlled environments, for their biotech manufacturing plant in Raheen, Co. Limerick. ​They required a new 38 kV substation compound for connection to a 38 kV ESB supply.

H&MV's Solution

  • H&MV were responsible for the design & build of a new 38 kV substation compound for connection to a 38 kV ESB supply. This included the design, supply, installation, integration, testing & commissioning of the complete 38kV substation system.
  • This also included the construction of a 38 kV substation compound, including the ESB 38 kV switch room, the client 20 kV switch room, earthing grid, access roadway, compound fence and electrical and mechanical services.
  • Installation of two 38 kV/20 kV outdoor power transformers and the supply and installation of 20 kV HV cable around the Eli Lily Limerick campus & between the ESB GIS switchgear to the 38 kV/20 kV transformers was also required.
Share this project

Similar Projects